Computation of Price Signals for Controlling Flexible Prosumers in Distribution Grids Incorporating Stochasticity and Fairness

Abstract

This paper proposes a method for distribution system operators (DSOs) to design spatially fair dynamic price signals for flexible prosumers, accounting for both distribution grid constraints and the stochastic behavior of prosumers. Since locational pricing can introduce price unfairness when grid constraints are active, the proposed approach includes mechanisms to enforce price fairness across the network. The method involves the DSO solving a scenario-based optimal power flow (OPF) problem to derive, similarly to locational marginal prices in transmission systems, the Lagrange multipliers associated with grid constraints and to compute individualized price signals for each prosumer under various PV generation and demand scenarios. Subsequently, two methods are introduced to aggregate these individualized prices into a single fair price across prosumers. Their performance is evaluated through simulations on a model distribution grid, comparing prosumer revenues, grid constraint violations, and analyzing the impact of fairness on reducing cost variance among prosumers.

Introduction

Behind-the-meter distributed energy resources (DERs), such as photovoltaic (PV) panels, battery energy storage systems (BESSs), and electric vehicles (EVs), enable passive consumers to become prosumers. By leveraging the flexibility of their DERs, prosumers can optimize their energy usage and supply valuable services to distribution system operators (DSOs), like congestion management and voltage control, provided that appropriate remuneration is available to do so.

Flexibility of behind-the-meter DERs can be activated either directly, through explicit requests to prosumers to change their demand, or indirectly, using price signals [1], [2]. Typical schemes for computing price signals include time-of-use (TOU) tariffs, which aim to shift demand to off-peak periods (e.g., [3], [4]), and real-time dynamic tariffs that adapt the price during the day according to the supply and demand [5]. Compared to explicit requests, price signals can be easily interpreted by the prosumers as they are provided with incentives to activate their flexibility at a specific time.

TOU and real-time tariffs typically do not consider the distribution grid constraints. As such, they can lead to synchronized prosumer behaviour, with many increasing or reducing demand simultaneously in response to price peaks and troughs, which in turn can cause over- or undert voltages or congestion in the grid’s lines. One way to prevent this issue is by using dynamic price signals that account not only for market conditions but also for the physical constraints of the distribution grid. This requires estimating potential grid violations, which inherently depend on the stochastic factors, such as electricity load and PV generation.

In this paper, we propose a method for computing price signals for prosumers that incorporates grid constraints in the prices and accounts for uncertainty in load and PV generation. The goal is to advertise a price signal to each prosumer, such that the prosumers’ responses to it respect the grid constraints for every possible realization of the system’s uncertainties. We also study the issue of fairness to mitigate locational disparities in the advertised price signals. The robustness and economic performance of the proposed pricing strategy are evaluated, providing insight into the costs the DSO incurs to respect the grid’s constraints and fairness among the system’s participants.

The price of the distribution’s grid constraints is typically estimated in the literature using the Distribution Locational Marginal Prices (DLMPs) method, which utilizes the Lagrange Multipliers of an Optimal Power Flow (OPF) to shift the original electricity price. Linear price signals, as those used in [6], can have multiple optimal solutions and do not guarantee fairness. The works in [7], [8] extend the notion of DLMPs to define quadratic price signals that are more stable than linear ones, whereas [9] addresses the problem by incorporating conic constraints in the Lagrangian. Uncertainty can also be incorporated into DLMP computation by solving robust OPFs, as in [10], [11], that consider the uncertainty sets of the system’s disturbances. However, uncertainty sets fail to capture the time dependence in time series. This can lead to higher costs than necessary, especially when time-dependent constraints are present in the system, as is the case with BESS. In this case, a scenario-based approach is more appropriate, as in [12], [13].

Our method handles uncertainty in the load profiles and PV generation by solving a scenario-based quadratic OPF. The DSO computes a price signal for each prosumer and for each scenario by extracting the Lagrange multipliers of the grid constraints for the respective scenario. To avoid multiplicity of solutions, the price signals are computed using the augmented Lagrangian, employed by the Alternating Direction Method of Multipliers (ADMM) [14], which includes a non-linear penalty on the grid’s constraints, thereby enhancing the stability of the solution. The works in [15], [16] use ADMM to solve OPFs in a distributed manner, but do not consider the interpretation of the Lagrangian as a price signal. On the other hand, [12], [17] utilize the interpretation of the Lagrange multipliers as marginal prices that incentivize the prosumers to change their demand. Our work expands on this interpretation by computing an explicit price signal for each prosumer, allowing them to interpret it outside the context of ADMM.

This paper builds upon our previous work in [18], which interprets the objective of ADMM as a price signal, but does not consider uncertainty. To account for the worst-case scenario of load and PV generation, the DSO aggregates the price signals computed for each scenario into a robust one by selecting the scenario with the price that differs the most from the original electricity price. The performance of the computed robust price signal is compared to a baseline price signal, which is computed by only considering the expected value of the load trajectories and PV generation.

Fairness is also an issue that arises from the different locations of prosumers in the grid, which is referred to as spatial fairness. Fairness in distribution grids has been studied in the context of PV curtailment (e.g., [19, 20, 21]). Prosumers located further from the feeder typically experience higher curtailment, as they have a greater impact on nodal voltages. In another context, [22] utilizes Jain’s fairness index to minimize price disparities among prosumers resulting from DLMPs, while [23] balances the costs of prosumers and grid constraints. [13] solves a scenario-based OPF that optimally allocates energy storage among the nodes, considering fairness in the prices experienced by the prosumers. In our work, we consider a fairness objective in the DSO’s optimization problem that minimizes the variance of the costs incurred by the prosumers for grid connection. The fairness is then transferred to the computed price signals. We finally perform an analysis of the effect of the degree of fairness on the total costs of the system and the grid constraints violations.

The rest of the paper is organized as follows. Section II formulates the centralized scenario-based optimization problem solved by the DSO. Section III described the method for computing the price signals for the prosumers. Section IV evaluates the performance of the computed price signals. Finally, Section V concludes the paper.

Optimization Problem Formulation

Use case and notation

We consider a low-voltage distribution grid interfacing NN prosumers. Each prosumer n∈{1,…,N}n \in\{1,\ldots,N\} is equipped with loads, PV panels, and a local BESS. The loads are assumed nonflexible, the PV generation is curtailable (if necessary), and the BESS operates in all four quadrants, providing both active and reactive power within the limits imposed by the power converter and the battery’s characteristics.

To optimize the use of the BESS energy capacity and maximize the available capacity for local and grid services, each prosumer schedules its operation day-ahead. To this end, we consider KK discrete steps tk∈{t1,…,tK}t_k \in\{t_1,\ldots,t_K\} of the next-day optimization horizon with resolution ΔT\Delta T, and SS day-ahead scenarios s∈{1,…,S}s \in\{1,\ldots,S\} of different combinations of prosumers’ demands and PV generation forecasts. We denote by {pl,ns(t),ql,ns(t)}\{p_{l,n}^{s}(t),q_{l,n}^{s}(t)\}, {ppv,ns(t),qpv,ns(t)}\{p_{pv,n}^{s}(t),q_{pv,n}^{s}(t)\}, {pb,ns(t),qb,ns(t)}\{p_{b,n}^{s}(t),q_{b,n}^{s}(t)\} the active and reactive power of the loads, the PV generation, and the BESS discharging power (negative if charging) for time step tt, prosumer nn, and scenario ss, respectively. We define the aggregated nodal demand of the prosumer as the tuple

xns(t)=[pl,ns(t)−ppv,ns(t)−pb,ns(t), ql,ns(t)−qpv,ns(t)−qb,ns(t)].(1)x_n^{s}(t) = [p_{l,n}^{s}(t) - p_{pv,n}^{s}(t) - p_{b,n}^{s}(t),\ q_{l,n}^{s}(t) - q_{pv,n}^{s}(t) - q_{b,n}^{s}(t)]. \tag*{(1)}

Although the proposed use case assumes the presence of the aforementioned flexible resources, the formulation is general and can accommodate additional resources.

Overview of the proposed control-by-price paradigm

It is assumed that the prosumers share with the DSO the specifications of their assets connected to the grid (as mandated by distribution grid codes in several countries) as well as real-time measurements. However, the DSO cannot directly control the behind-the-meter flexibility, which remains fully under the prosumers’ control. Instead, the DSO can influence prosumers’ consumption patterns through a dynamic price signal.

In particular, the DSO, capitalizing on its full observability, solves a scenario-based centralized OPF and extracts the Lagrange multipliers associated with the active grid constraints of each scenario. These multipliers serve as locational price signals, indicating the marginal cost of enforcing network constraints. To ensure usability, each prosumer receives a single, time-varying price signal. This is derived by aggregating the scenario-specific multipliers into one representative signal per prosumer. Finally, the prosumer optimizes its own energy consumption, driven by the new price signal and unaware of any grid constraints.

The rest of this section presents the centralized optimization problem that the DSO must solve. The price signals is presented in Section III.

Prosumer Objective

The goal of the prosumers is to minimize their electricity bill. Given a forecast of the retail electricity price c=[ct1,0,…,ctK,0]T\mathbf{c} = [c_{t_1},0,\ldots,c_{t_K},0]^{\mathsf{T}}, where the zeros correspond to the price of reactive power, the forecast electricity cost paid by prosumer nn for scenario ss is the following

Cns=cTxns(2)C_n^s = \mathbf{c}^{\mathsf{T}}\mathbf{x}_n^s \tag*{(2)}

where xns=[xns(t1),…,xns(tK)]T\mathbf{x}_n^s = [x_n^s(t_1),\ldots,x_n^s(t_K)]^{\mathsf{T}} is the collection of the aggregated demand for all time instances.

PV Constraints

We denote by Gns(t)∈[0,1]G_n^s(t) \in[0,1] the per-unit forecasts of PV generation at the location of prosumer nn for time tt and scenario ss. The active powers of the PV panels are bounded by the following constraints

0≤ppv,ns(t)≤ppv,nmax⁡Gns(t)(3)0 \leq p_{pv,n}^s(t) \leq p_{pv,n}^{\max}G_n^s(t) \tag*{(3)}

where ppv,nmax⁡p_{pv,n}^{\max} is the maximum power of the PV of prosumer nn. For simplicity, we assume that the PV panels only offer active-power flexibility, so we consider

qpv,ns(t)=0, ∀n,t,s(4)q_{pv,n}^s(t) = 0,\ \forall n,t,s \tag*{(4)}

BESS Constraints

We use a box approximation of the PQ capability curve of the BESS’s converter in the four quadrants:

−sb,nmax⁡≤2⋅pb,ns(t)≤sb,nmax⁡(5)-s_{b,n}^{\max} \leq\sqrt{2}\cdot p_{b,n}^s(t) \leq s_{b,n}^{\max} \tag*{(5)}
−sb,nmax⁡≤2⋅qb,ns(t)≤sb,nmax⁡(6)-s_{b,n}^{\max} \leq\sqrt{2}\cdot q_{b,n}^s(t) \leq s_{b,n}^{\max} \tag*{(6)}

where sb,nmax⁡s_{b,n}^{\max} is the maximum apparent power of the converter. The state of charge (SOC) of the BESS is defined as a time coupling constraint, which connects the current BESS capacity to its power history. The SOC is also limited to ensure safe operations and to enhance battery life, within a range [SoCnmin⁡,SoCnmax⁡]=[10%,90%][SoC_n^{\min},SoC_n^{\max}] = [10\%,90\%]. The SOC with unitary efficiency model reads as:

SoCns(t)=SoCn(t1)−ΔTEb,n∑τ=t1t−1pb,ns(τ)(7)SoC_n^s(t) = SoC_n(t_1) - \frac{\Delta T}{E_{b,n}}\sum_{\tau=t_1}^{t-1}p_{b,n}^s(\tau) \tag*{(7)}
SoCnmin⁡≤SoCns(t)≤SoCnmax⁡(8)SoC_n^{\min} \leq SoC_n^s(t) \leq SoC_n^{\max} \tag*{(8)}

where SoCn(t1)SoC_n(t_1) is the initial SoC for prosumer nn (same for all scenarios) and Eb,nE_{b,n} is the energy capacity of the BESS. Non-unity efficiencies can be modeled using relaxations or mixed-integer formulations with binary variables, as is well established in the literature. Since their inclusion is straightforward and does not affect our main contributions, we omit them here for clarity of exposition.

Grid Constraints

The goal of the DSO is to maintain all the nodal voltages within defined limits [vmin⁡,vmax⁡][v^{\min},v^{\max}] and to respect the current limits at all branches and power constraints at the grid connection point (GCP). We denote by vjs(t)v_j^s(t), j∈{1,…,M}j \in\{1,\ldots,M\} the voltage at node jj, at time tt for scenario ss, where MM is the number of nodes in the grid. The relation between nodal power injections and voltages is expressed using the following linearized approximation

vjs(t)=vjs∗+Kv,ps(t)(ps(t)−ps∗(t))+Kv,qs(t)(qs(t)−qs∗(t)),(9)v_j^s(t) = v_j^{s*} + K_{v,p}^s(t)(\mathbf{p}^s(t)-\mathbf{p}^{s*}(t)) + K_{v,q}^s(t)(\mathbf{q}^s(t)-\mathbf{q}^{s*}(t)), \tag*{(9)}

where ps(t)\mathbf{p}^s(t) and qs(t)\mathbf{q}^s(t) are the vectors of all the nodal active and reactive power injections, and ps∗(t)\mathbf{p}^{s*}(t), qs∗(t)\mathbf{q}^{s*}(t) and vs∗\mathbf{v}^{s*} are the injections and voltages at the grid linearization point, respectively. The latter is computed with a load flow at the reference power injections; Kv,ps(t),Kv,qs(t)K_{v,p}^s(t),K_{v,q}^s(t) are the matrices of the sensitivity coefficients of the voltages with respect to the active and reactive powers, computed around the reference points. The sensitivity coefficients are the derivatives of the nodal voltages with respect to the active and reactive nodal power injections and can be computed analytically [24]. The linearized voltage constraints can then be expressed by

vmin⁡≤vjs(t)≤vmax⁡.(10)v^{\min} \leq v_j^s(t) \leq v^{\max}. \tag*{(10)}

Similarly, we define the constraints of the linearized branch current magnitudes ils(t)i_l^s(t), l∈{1,…,L}l \in\{1,\ldots,L\}, where LL is the number of branches in the grid, and the linearized slack’s active and reactive power p0s(t),q0s(t)p_0^s(t),q_0^s(t). The linear approximations for the branch currents and the slack’s power are given by equations similar to (5a). The current magnitude constraints can be written as

0≤ils(t)≤ilmax⁡(11)0 \leq i_l^s(t) \leq i_l^{\max} \tag*{(11)}

where ilmax⁡i_l^{\max} is the ampacity rating of branch ll. The power constraints at the slack bus are typically expressed as a power factor constraint. However, the power factor definition is non-convex, even after linearizing the power flow equations. To avoid non-convexity, we use a tight upper bound q0max⁡q_0^{\max} for the slack’s reactive power

q0s(t)≤q0max⁡,(12)q_0^s(t) \leq q_0^{\max}, \tag*{(12)}

where q0max⁡≪s0max⁡q_0^{\max} \ll s_0^{\max} and s0max⁡s_0^{\max} is the transformer’s maximum apparent power at the GCP. Then, the active power limit is defined as

p0s(t)≤(s0max⁡)2−(q0max⁡)2(13)p_0^s(t) \leq\sqrt{(s_0^{\max})^2-(q_0^{\max})^2} \tag*{(13)}

In the following, we group all the DSO’s constraints into the following equations

Aeq,sXs=beq,s(14)A^{eq,s}\mathbf{X}^s = \mathbf{b}^{eq,s} \tag*{(14)}
Aineq,sXs≤bineq,s,(15)A^{ineq,s}\mathbf{X}^s \leq\mathbf{b}^{ineq,s}, \tag*{(15)}

where Xs\mathbf{X}^s is the matrix of all the prosumers’ aggregated power injections xns\mathbf{x}_n^s for scenario ss; Aeq,sA^{eq,s}, Aineq,sA^{ineq,s} are the equality and inequality linearization matrices, and beq,s,bineq,s\mathbf{b}^{eq,s},\mathbf{b}^{ineq,s} are the linearization vectors of the grid constraints for scenario ss. This formulation will be useful in computing the price signals in Section III.

Centralized Problem’s Objective

The problem objective is to minimize the prosumers’ total energy bills while respecting the distribution grid’s constraints. It is assumed that the DSO has no monetary objective of its own, but may consider fairness, as developed later.

The expected monetary cost of the system is the total cost of the prosumers, averaged over all scenarios:

Jc=1S∑s=1S∑n=1NcTxns.(16)\mathcal{J}^{c} = \frac{1}{S}\sum_{s=1}^{S}\sum_{n=1}^{N}\mathbf{c}^{T}\mathbf{x}_{n}^{s}. \tag*{(16)}

Due to the grid constraints, the costs incurred by prosumers will be higher compared to the unconstrained case. We measure fairness by the variance of the cost increases among prosumers compared to the unconstrained case. We denote by p^ns\hat{\mathbf{p}}_{n}^{s} the vector of the active powers p^ns(t)\hat{p}_{n}^{s}(t) that minimize the objective of prosumer nn (2) subject to the prosumer’s constraints (3) and (4) for scenario ss. Then, the cost increase of the prosumer at time tt is defined as

ΔCns(t)=ct(pns(t)−p^ns(t)).(17)\Delta C_{n}^{s}(t) = c_{t}\left(p_{n}^{s}(t)-\hat{p}_{n}^{s}(t)\right). \tag*{(17)}

Then, the fairness objective of the DSO is defined as

Jf=1S∑s=1,t=t1S,tKVar⁡(ΔCns(t)),(18)\mathcal{J}^{f} = \frac{1}{S}\sum_{s=1,t=t_{1}}^{S,t_{K}} \operatorname{Var}\left(\Delta C_{n}^{s}(t)\right), \tag*{(18)}

where Var⁡(⋅)\operatorname{Var}(\cdot) is the sample variance among the prosumers.

Centralized Problem Formulation

The vector of the optimization variables for all timesteps of prosumer nn and scenario ss is

x~ns=[pb,ns;qb,ns;ppv,ns;qpv,ns;socns](19)\tilde{\mathbf{x}}_{n}^{s} = [\mathbf{p}_{b,n}^{s};\mathbf{q}_{b,n}^{s};\mathbf{p}_{pv,n}^{s};\mathbf{q}_{pv,n}^{s};\mathbf{soc}_{n}^{s}] \tag*{(19)}

where [⋅;⋅][\cdot;\cdot] denotes vertical concatenation of vectors, or matrices. The centralized OPF is formulated as follows

min⁡xns,x~nsJc+wfJf+αS∑n=1,s=1N,S∥pb,ns∥22(20)\min_{\mathbf{x}_{n}^{s},\tilde{\mathbf{x}}_{n}^{s}} \quad\mathcal{J}^{c}+w^{f}\mathcal{J}^{f}+\frac{\alpha}{S}\sum_{n=1,s=1}^{N,S}\lVert\mathbf{p}_{b,n}^{s}\rVert_{2}^{2} \tag*{(20)}

subject to: \quad PV constraints (3) {#eq:11b}

BESS constraints (4) {#eq:11c}

Linear grid constraints (6) {#eq:11d}

∀n∈{1,…,N},s∈{1,…,S}\forall n \in\{1,\ldots,N\}, s \in\{1,\ldots,S\}, {#eq:11e}

where wfw^{f} is the weight of the fairness objective, and the terms ∥pb,ns∥22\lVert\mathbf{p}_{b,n}^{s}\rVert_{2}^{2} with weight α\alpha are small penalties on the BESS power that prevent the multiplicity of solutions inherent to linear problems. Problem (11) is convex, because the variance and norm are convex and all the constraints are linear.

To minimize the error of the linearized model, we recompute the linearization matrices until the linearization error of the grid constraints is below a given tolerance ϵ\epsilon. We aggregate the matrices Aeq,s,Aineq,s,beq,s,bineq,s,XsA^{eq,s}, A^{ineq,s}, b^{eq,s}, b^{ineq,s}, X^{s}, into matrices Aeq,Aineq,beq,bineq,XA^{eq}, A^{ineq}, b^{eq}, b^{ineq}, X containing the respective matrices for all scenarios. We also define

A=[Aineq;Aeq](21)A = [A^{ineq};A^{eq}] \tag*{(21)}
b=[bineq;beq].(22)b = [b^{ineq};b^{eq}]. \tag*{(22)}

We denote by geq(X),gineq(X)\mathbf{g}^{eq}(\mathbf{X}),\mathbf{g}^{ineq}(\mathbf{X}) the vectors of the non-convex inequality and equality grid constraints evaluated at the set of setpoints X\mathbf{X}, such that X\mathbf{X} are feasible if geq(X)=0\mathbf{g}^{eq}(\mathbf{X})=0 and geq(X)≤0\mathbf{g}^{eq}(\mathbf{X})\leq0. Then, the linearization error of the grid constraints is defined by the norm

∥AX−b−g(X)∥2,(23)\lVert A\mathbf{X}-b-\mathbf{g}(\mathbf{X})\rVert_{2}, \tag*{(23)}

where g(X)=[geq(X);gineq(X)]\mathbf{g}(\mathbf{X})=[\mathbf{g}^{eq}(\mathbf{X});\mathbf{g}^{ineq}(\mathbf{X})].

The algorithm for approximating the solution of the non-convex OPF by sequentially solving a series of linearised OPFs is summarized in Algorithm 1, where the superscript kk is used to indicate the iteration number. It should be noted that (11) is separable with respect to the scenarios so that we can solve SS simpler problems, one for each scenario.

Algorithm 1 Sequential Linearization of OPF

  1. Input: load and PV generation scenarios pl,ns(t)p_{l,n}^{s}(t), ql,ns(t)q_{l,n}^{s}(t), Gns(t)G_{n}^{s}(t). Grid topology. Convergence tolerance ϵ\epsilon.

  2. Output: aggregated demands xnsx_{n}^{s}, optimal resources set-points x~ns\tilde{x}_{n}^{s}, constraint matrices AA and bb, Lagrange multipliers λk\lambda^{k}

  3. k←1k \leftarrow1

  4. initialize Xk,Ak,bk\mathbf{X}^{k}, A^{k}, b^{k}

  5. while ∥AkXk−bk−g(Xk)∥2>ϵ\lVert A^{k}\mathbf{X}^{k}-b^{k}-\mathbf{g}(\mathbf{X}^{k})\rVert_{2}>\epsilon do

  6. Solve (11) with (Aeq,s)k(x)=(beq,s)k, ∀s(A^{eq,s})^{k}(\mathbf{x})=(b^{eq,s})^{k},\ \forall s

    (Aineq,s)k(x)≤(bineq,s)k, ∀s,(A^{ineq,s})^{k}(\mathbf{x})\leq(b^{ineq,s})^{k},\ \forall s,

    to get the optimal demands (xns)k(\mathbf{x}_{n}^{s})^{k}, resources setpoints (x~ns)k(\tilde{\mathbf{x}}_{n}^{s})^{k} and Lagrange multipliers λk\lambda^{k} and compute the nodal power injections Xk+1\mathbf{X}^{k+1}

  7. Recompute Ak,bkA^{k},b^{k} around Xk+1\mathbf{X}^{k+1}

  8. k←k+1k \leftarrow k+1

  9. end while

  10. return (xns)k,(x~ns)k,Ak,bk,λk(\mathbf{x}_{n}^{s})^{k},(\tilde{\mathbf{x}}_{n}^{s})^{k},A^{k},b^{k},\lambda^{k}

Price Signal Computation

Lagrangian

Instead of advertising the resources’ setpoints x~ns\tilde{\mathbf{x}}_{n}^{s} directly to the prosumers, the DSO computes a price signal for the aggregated demand xn\mathbf{x}_{n}. These price signals are computed such that they represent, in addition to the original price, potential grid-constraints violations. Suppose the prosumers optimize their operation given the original price c\mathbf{c}. In that case, their decisions might violate the grid’s constraints, because the prosumers’ behaviours will be synchronized according to the dynamics of c\mathbf{c}. Therefore, the goal of the DSO is to shift the optimal operation schedule of each prosumer towards one that allows for safe grid operations by advertising separate price signals to each one.

We formulate these price signals using the augmented Lagrangian for the grid constraints of the linearized centralized problem (11) defined in [14]. The formulation follows a similar methodology as in [18]. The Augmented Lagrangian of the problem moves the coupling constraints of (6) to the cost function as follows

L(X)=Jc+wfJf+λT(AX−b)+ρ2∥AeqX−beq∥22+ρ2∥max⁡(AineqX−bineq,0)∥22.(24)\mathcal{L}(\mathbf{X}) = \mathcal{J}^{c} + w^{f}\mathcal{J}^{f} + \boldsymbol{\lambda}^{\mathsf{T}}(A\mathbf{X}-\mathbf{b}) + \frac{\rho}{2}\left\lVert A^{eq}\mathbf{X}-\mathbf{b}^{eq}\right\rVert_{2}^{2} + \frac{\rho}{2}\left\lVert\max(A^{ineq}\mathbf{X}-\mathbf{b}^{ineq},0)\right\rVert_{2}^{2}. \tag*{(24)}

The first two terms represent the original cost of the system. The penalty on the BESSs power is omitted, and instead is incorporated into the prosumers’ optimization problems (see Section III-B). The third term attempts to enforce the feasibility of the dual problem. The last two terms are additional quadratic penalties on the constraint satisfaction with weight ρ\rho that help with stability. Minimizing (14) subject to the prosumers’ constraints (3) and (4) should give the solution to the centralized problem (11). Therefore, it can be perceived as a price signal that enforces the grid constraints.

However, (14) includes some coupling terms, so it cannot be used to extract separate price signals. The cost Jc\mathcal{J}^{c} is separable among the prosumers and can be written as a sum of the individual monetary costs

Jnc=1S∑s=1ScTxns.(25)\mathcal{J}_{n}^{c} = \frac{1}{S}\sum_{s=1}^{S}\mathbf{c}^{\mathsf{T}}\mathbf{x}_{n}^{s}. \tag*{(25)}

On the other hand, the fairness penalty Jf\mathcal{J}^{f} cannot be separated because of coupling terms in the variance. To split the costs, we use an approximation of the variance of the cost increases as follows

Var⁡(ΔCns(t))≈1N∑n=1N(ΔCns(t)−μs(t))2,(26)\operatorname{Var}(\Delta C_{n}^{s}(t)) \approx\frac{1}{N}\sum_{n=1}^{N}\left(\Delta C_{n}^{s}(t)-\mu^{s}(t)\right)^{2}, \tag*{(26)}

where

μs(t)=1N∑n=1NΔCˉns(t),(27)\mu^{s}(t)=\frac{1}{N}\sum_{n=1}^{N}\Delta\bar{C}_{n}^{s}(t), \tag*{(27)}

and ΔCˉns(t)\Delta\bar{C}_{n}^{s}(t) is the value of ΔCns(t)\Delta C_{n}^{s}(t) computed by solving the centralized problem (11) for scenario ss. Therefore, we approximate the expected value of the prosumers’ costs as the average of the optimal costs over all prosumers. (16) is now separable among prosumers, because μs(t)\mu^{s}(t) is a constant (it does not depend on ΔCns(t)\Delta C_{n}^{s}(t)).

To separate the last two terms of (14), we use ideas inspired by the method of dual decomposition [14]. First, we partition the matrix AA column-wise as follows

A=[A1⋯AN],(28)A = \begin{bmatrix} A_{1} & \cdots& A_{N} \end{bmatrix}, \tag*{(28)}

where AnA_{n} contains the columns of AA corresponding to prosumer nn. We also introduce the auxiliary variables:

zns=Ansxˉns,(29)z_{n}^{s}=A_{n}^{s}\bar{x}_{n}^{s}, \tag*{(29)}

with xˉns\bar{x}_{n}^{s} being the solution of the centralized problem for prosumer nn and scenario ss and AnsA_{n}^{s} contains the rows of AnA_{n} that correspond to the grid constraints tied with scenario ss.

Then, the augmented Lagrangian of prosumer nn and scenario ss can be defined as:

Lns(xns)=cTxns+wfN∥cT(xns−x^ns)−μs∥22+(λns)T(Ansxns−zns)+ρ2∥Ansxns−zns∥22,(30)\mathcal{L}_{n}^{s}(x_{n}^{s})=\mathbf{c}^{\mathsf{T}}x_{n}^{s}+\frac{w^{f}}{N}\left\lVert\mathbf{c}^{\mathsf{T}}(x_{n}^{s}-\hat{x}_{n}^{s})-\mu^{s}\right\rVert_{2}^{2}+\left(\lambda_{n}^{s}\right)^{\mathsf{T}}\left(A_{n}^{s}x_{n}^{s}-z_{n}^{s}\right)+\frac{\rho}{2}\left\lVert A_{n}^{s}x_{n}^{s}-z_{n}^{s}\right\rVert_{2}^{2}, \tag*{(30)}

where x^ns\hat{x}_{n}^{s} are the solutions of the unconstrained problems and μs\mu^{s} is the vector of μs(t)\mu^{s}(t). Reformulation of this augmented Lagrangian highlights the quadratic nature of the cost.

Lns(xns)=[c⊙(1−wfNμs)+(Ans)Tλns−ρ(Ans)Tzns]Txns+(xns)T[ρ2(Ans)TAns+wfNdiag⁡(c)]xns+const⁡,(31)\mathcal{L}_{n}^{s}(x_{n}^{s}) = \left[\mathbf{c}\odot\left(\mathbf{1}-\frac{w^{f}}{N}\mu^{s}\right)+(A_{n}^{s})^{\mathsf{T}}\lambda_{n}^{s}-\rho(A_{n}^{s})^{\mathsf{T}}z_{n}^{s}\right]^{\mathsf{T}}x_{n}^{s} +\left(x_{n}^{s}\right)^{\mathsf{T}}\left[\frac{\rho}{2}(A_{n}^{s})^{\mathsf{T}}A_{n}^{s}+\frac{w^{f}}{N}\operatorname{diag}(\mathbf{c})\right]x_{n}^{s}+\operatorname{const}, \tag*{(31)}

where 1\mathbf{1} is a vector with all elements 1, ⊙\odot indicates element-wise multiplication of vectors and diag⁡(c)\operatorname{diag}(\mathbf{c}) is a diagonal matrix with the elements of c\mathbf{c} in the diagonal. Expression (22) is in the standard form of the cost function of a quadratic program:

Lns(xns)=(c~ns)Txns+12(xns)TQnsxns+C~ns,(32)\mathcal{L}_{n}^{s}(x_{n}^{s})=(\tilde{\mathbf{c}}_{n}^{s})^{\mathsf{T}}x_{n}^{s}+\frac{1}{2}(x_{n}^{s})^{\mathsf{T}}Q_{n}^{s}x_{n}^{s}+\tilde{C}_{n}^{s}, \tag*{(32)}

where c~ns\tilde{\mathbf{c}}_{n}^{s} is the modified price that considers the grid constraints and fairness, QnsQ_{n}^{s} is a price on the square of the demand, which helps with stability and fairness, and C~ns\tilde{C}_{n}^{s} is a constant cost that can be interpreted as a fee for grid connection.

The stochastic variables introduce uncertainty in the price signal computation, resulting in multiple Lagrangians, one for each scenario. However, the DSO should provide only one price signal to the prosumers. We compare two approaches to aggregate the Lagrangians into a single representative price signal.

  1. Method 1: expected scenarios: The augmented Lagrangian is computed using the average load and PV generation among all scenarios. For this method, there is only one scenario in (11), resulting in a single Lagrangian for each prosumer.

  1. Method 2: robust price signal: The expected scenario may result in grid-constraints violations because it does not account for the worst-case scenario. In this method, we aim to compute a worst-case price signal to ensure the grid constraints are respected for every possible scenario of the load and PV generation. The computation relies on the idea that the modified price c~ns\tilde{c}_{n}^{s} will differ from the original price c\mathbf{c} when there are binding constraints in the system. Therefore, for each timestep, we select the coefficients of the Lagrangian for the scenario whose linear price signal component is most different from the original price. Formally, the robust price signal tt is given as follows

Lnrobust(t2n−1)={Lns(t2n−1):min⁡s∣c~ns(t2n−1)−ctn∣}(33)\mathcal{L}_{n}^{robust}(t_{2n-1})=\left\{\mathcal{L}_{n}^{s}(t_{2n-1}):\min_{s}\left|\tilde{c}_{n}^{s}(t_{2n-1})-c_{t_{n}}\right|\right\} \tag*{(33)}
Lnrobust(t2n)={Lns(t2n):min⁡s∣c~ns(t2n)∣},(34)\mathcal{L}_{n}^{robust}(t_{2n})=\left\{\mathcal{L}_{n}^{s}(t_{2n}):\min_{s}\left|\tilde{c}_{n}^{s}(t_{2n})\right|\right\}, \tag*{(34)}
ParameterValue
Max Load2.5 kW
Max PV power6 kW
Rated BESS power4 kVA
BESS energy capacity4 kWh

Table 1. Power and energy ratings of prosumers

where the elements of the price signal with odd indices correspond to the active power coefficients and the even ones correspond to the reactive power coefficients (the original price for the reactive power is 0). The two methods are compared in terms of achieved costs, constraints violations, and fairness in § 5.

Finally, we should note that the above formulation of price signals is general and can be applied to additional types of resources and grid constraints beyond those defined in § 2. The only limitation is that the grid model must be linear, so that the grid constraints are separable.

Individual problem formulation

Using one of the two proposed methods, the DSO computes one price signal per prosumer of a quadratic nature. The linear, quadratic, and constant parts for prosumer nn are respectively expressed by c~n\tilde{c}_n, QnQ_n, and C~n\tilde{C}_n. Then, the prosumers schedule their demand by minimizing this cost independently and unaware of grid constraints. The optimization problem to be solved by each prosumer is the following

min⁡x~n,xnc~n⊤xn+12xn⊤Qnxn+C~n+α∥pb,n∥22(35)\min_{\tilde{x}_n,x_n} \quad\tilde{c}_n^{\top}x_n+\frac{1}{2}x_n^{\top}Q_nx_n+\tilde{C}_n+\alpha\lVert p_{b,n}\rVert_2^2 \tag*{(35)}

subject to: \quad PV constraints (3)

PV constraints (3)(36)\text{PV constraints (3)} \tag*{(36)}
BESS constraints (4)(37)\text{BESS constraints (4)} \tag*{(37)}

where the prosumer only considers a single scenario of the load and PV generation. In the following section, we examine the outcome when prosumers solve (26) for various combinations of scenarios. We should note that the prosumers themselves could solve a scenario-based optimization problem to determine their scheduled demand. This could be studied in future research.

LineResistance (mΩ\Omega)Reactance (mΩ\Omega)
Z1Z_1585.1305.7
Z2Z_2194.1161.3
Z3Z_3216.1177.8
Z4Z_42000
Z5Z_5597.0296.2
Z6Z_6194.4166.4

Table 2. Line parameters

Validation

Case Study

We validate the proposed price signals via simulations on a low-voltage, three-phase, radial distribution grid implemented in the Gridlab laboratory at HES-SO Valais in Sion (Switzerland), as shown in Figure 1. Node N1 is connected to the external grid and serves as the system’s slack bus. Five prosumers are connected to nodes N2, N3, N4, N6, and N7, each one owning a curtailable PV and a BESS. The power and energy rating of the prosumers’ assets are the same and are shown in Table I. The line impedances, shown in Table II, are estimated from measurements of the experimental setup as described in [25].

Grid topology for the experimental validation

Figure 1. Grid topology for the experimental validation. N1 is the connection point with the upper grid.

The voltage limits of the system are set to [0.9, 1.05]pu. The transformer’s rating at the GCP is 15 kVA. The maximum reactive power at the slack bus is set to q0max⁡=0.1s0max⁡q_0^{\max}=0.1s_0^{\max}, which gives a power factor of over 0.99 when the exported power to the main grid is maximum. Because we focus the performance evaluation on potential voltage-constraints violations, we set very high limits for the ampacity limits of the grid’s lines. The simulations are performed in MATLAB, and the optimization problems are solved with Gurobi. Because this study focuses on price control and fairness, the grid is assumed balanced and is modeled using a single-phase equivalent.

Scenarios Definitions

We consider 10 actual day-ahead forecasts (2 for each prosumer) of the active and reactive electrical load of office buildings on a weekday. These forecasts have a 10-minute resolution and are characterised by real prediction errors. We also consider two normalized PV-generation profiles scaled such that their maximum values are 1 and 0.7, respectively. The normalized PV profiles are the same for all prosumers. We then generate S=64S=64 scenarios by considering all possible combinations of the scenarios for the five prosumers’ loads and the two scenarios for the PV generation. These scenarios, referred to as “training scenarios”, will be used by the DSO to solve the centralized optimization problem and compute the price signals according to the method of § 2 and III.

We also consider two load scenarios for each prosumer, sampled from the same distribution as the training ones, but not used to compute the price signals. These scenarios, referred to as “test scenarios”, are used to solve the individual problems (26) to assess whether the computed price signals can respect the grid constraints in cases that the optimizer has not seen.

The PV scenarios of the test cases are identical to those in the training scenarios.

Evaluation Method

The performance of the computed price signals is evaluated in terms of the costs experienced by the prosumers and the size of the potential voltage-constraints violations. The evaluation procedure is as follows: We first use the 64 training scenarios to solve the prosumers’ individual optimization problems without any grid constraints (base case). We then use the same scenarios to solve the DSO’s optimization problem, computing the 64 price signals, which are then aggregated into the robust price signal. We also use the average of the scenarios to compute the expected price signal. We solve (26) independently for each prosumer, using both the expected and robust price signals for each of the training and test scenarios. We finally use the computed aggregated demands xnx_n to calculate the expected cost incurred by each prosumer for each scenario, as well as the expected voltage-constraint violations resulting from the scheduled demands.

The performance of the expected and robust price signals is evaluated independently on the training and test scenarios using the following metrics:

  1. Total cost increase in $ of the system compared to the base case (no grid constraints), averaged over all scenarios.

  2. Standard deviation of the prosumers’ cost increases from the base case as a percentage of the total cost increase. This is the metric of fairness.

  3. Maximum voltage constraints violation in pu over all nodes and scenarios.

Comparison Between Expected and Robust Price Signals

In this section, we compare the performance of the expected and robust price signals to assess whether they can respect the grid constraints while keeping the costs low. We use ρ=10\rho= 10 as the penalty on the grid constraints in the computation of the Lagrangian and ignore the fairness consideration, so wf=0w^f = 0. The effect of ρ\rho and wfw^f on the performance will be studied in the following section. The penalty α\alpha on the BESS power is set to 10−310^{-3}.

Figure 2 shows the modified electricity tariffs for one scenario for which voltage constraints are binding (due to high PV generation and low loads). The original electricity price is the highest between 7 a.m. and 5 p.m., because that is the period when office buildings are the busiest. The price decreases during daytime, because of the high expected PV generation. The price computed by the DSO is lower than the original price at the beginning of the day, which incentivizes prosumers to charge their BESSs and sell their stored energy later when the price peaks. Selling the stored energy at this point offers a double benefit, as the prosumers benefit from the high price and can also absorb the incoming energy produced by the PVs. During the day, the prices advertised by the DSO are also low, so the prosumers can consume more. The price for prosumers

Figure 2. Modified electricity tariffs for (a) active power and (b) reactive power for a single scenario.

at nodes N6 and N7, which are further away from the feeder, is negative, potentially resulting in PV curtailment.

Examining the price for reactive power, we observe that the DSO can effectively compute incentives for prosumers to produce or consume reactive power in accordance with the grid’s constraints. In particular, prosumers located farther from the feeder are incentivized to consume reactive power, thereby lowering the nodal voltages. In contrast, the other nodes need to produce reactive power to balance the production of the first prosumers.

Figure 3 shows the various performance metrics for the expected and robust price signals used on the training and test scenarios. The robust price signal results in a cost 10 times higher than the expected price signal. However, the robust price signal achieves significantly lower violations, which are below 1% of the nominal value for the training scenarios. In contrast, the violations observed with the expected price signal constitute a significant percentage of the system’s tolerance. Therefore, the cost increase imposed in the robust case is necessary to respect the voltage constraints. The maximum violation on the test scenarios is almost 3 times larger compared to the training scenarios. This implies that some of the worst-case scenarios have not been taken into account in the optimization problem. By considering more varied scenarios of the load profiles, we can prevent these worst cases.

Figure 3. Performance metrics for the expected and robust price signals evaluated on the training and test scenarios. (a) Total cost increase from the base case averaged over all scenarios, (b) average cost per prosumer, (c) maximum voltage violation over all scenarios.

fig:3b gives an insight into the fairness considerations of the computed price signals. We observe that, when fairness is not considered in the price signals, the prosumers at nodes N6 and N7 bear the overwhelming majority of the cost of the grid constraints. This is because these nodes have the most significant impact on the voltages, so it is more cost-effective to curtail the PVs of these prosumers to respect the voltage upper bound. Therefore, the DSO must consider fairness in the price signals it advertises to prosumers to avoid a single prosumer bearing the entire cost of the grid.

Effect of ρ\rho and Fairness

In this section, we compute the performance metrics for different combinations of the penalty ρ\rho and the fairness weight wfw^f, in the range [1, 10, 1000]. Figure 4 represents the values of the cost increase, the standard deviation of cost increases (expressed as a percentage of the total cost), and the maximum voltage violations achieved by the expected and robust price signals for the training and test scenarios. First, we observe a trend of increasing fairness (decreasing variance of costs)

Figure 4. Performance metrics for (a) training and (b) test scenarios for the robust and expected price signals. Each data point represents a different combination of the penalty ρ\rho on the grid constraints and fairness weight wfw^f.

as total costs increase. This is expected because equal cost-bearings can only be achieved by increasing the costs of the system. Moreover, the robust signal achieves worse fairness performance compared to the expected one for the same total cost; on the other hand, it achieves smaller voltage violations (the diamond points are darker shades of blue). This happens because the robust price signal considers the worst-case scenario, in which fairness might be sacrificed in favour of voltage control.

Looking at Figure 4a, we can make the following observations. If fairness is not necessary, which might be the case if the DSO remunerates the prosumers for their curtailment, then the robust price signal can achieve small average costs, around $1-2 higher than the base case, while keeping the voltage violations smaller than 1% of the nominal value. These costs can be achieved with a small fairness weight and a high value of ρ\rho. On the other hand, although the expected price signal achieves lower costs, it fails to regulate the voltages in the worst-case scenario. If, however, fairness is desirable, the expected price signal can achieve similar performance in terms of voltage regulation and fairness, but with smaller average costs ($5.2 instead of $6.2) in the system, provided that both ρ\rho and wfw^f are high. Therefore, the expected price signal can also achieve acceptable voltage regulation if paired with a high penalty ρ\rho on the grid constraints.

Similar observations can be made for the performance on the test scenarios. In this case, a good trade-off between fairness and costs can be achieved by both methods with an added average cost of $8 and violations smaller than 1%. However, the performance will depend on the similarity of the test scenarios to the training ones.

Conclusion

We have proposed a method for computing price signals that enables prosumers to provide flexibility to the DSO, thereby respecting the distribution grid’s constraints under uncertain operation. The method entails solving a scenario-based optimal power flow for different scenarios of the prosumers’ demand and their PV generation, which also accounts for fairness in the costs experienced by the prosumers. The DSO then computes a representative price signal for each prosumer that incorporates the grid’s constraints and fairness.

We compare the performance of two methods for aggregating the computed price signals, resulting in an expected price signal and a robust one, using simulations in a model distribution grid. The validation assesses the ability of the two signals to adhere to the bounds of the nodal voltages while maintaining low costs and achieving a fair distribution of costs among prosumers. The expected price signal generally results in lower costs than the robust one, but fails to meet the required voltage constraints. Regarding fairness, both price signals can achieve a low variance of the prosumers’ costs if the weights of the different objectives are carefully selected.

The scalability of the proposed method still requires thorough evaluation. Although the complexity of computing price signals scales linearly with the number of scenarios, the scenarios can scale exponentially with the number of nodes if all possible combinations among prosumers are considered. We should, therefore, carefully select the representative scenarios that account for the worst-case scenario of the system.

References

  1. [1]J. S. Vardakas, N. Zorba, and C. V. Verikoukis, “A survey on demand response programs in smart grids: Pricing methods and optimization algorithms,” IEEE Communications Surveys & Tutorials, vol. 17, no. 1, pp. 152–178, 2015.DOI
  2. [2]F. Sossan, M. Marinelli, G. T. Costanzo, and H. Bindner, “Indirect control of dsr for regulating power provision and solving local congestions,” in 2013 4th International Youth Conference on Energy (IYCE), 2013, pp. 1–5.DOI
  3. [3]N. Venkatraman, G. Hug, C. Schaffner, and M. G. Vayá, “Optimal design of time-of-use tariffs using bilevel optimization,” in 2022 IEEE PES Innovative Smart Grid Technologies Conference Europe (ISGT-Europe), 2022, pp. 1–5.
  4. [4]V. Sharma, S. M. Aziz, M. H. Haque, and T. Kauschke, “Energy economy of households with photovoltaic system and battery storage under time of use tariff with demand charge,” IEEE Access, vol. 10, pp. 33 069–33 082, 2022.
  5. [5]M. L. Nicolson, M. J. Fell, and G. M. Huebner, “Consumer demand for time of use electricity tariffs: A systematic review of the empirical evidence,” Renewable and Sustainable Energy Reviews, vol. 97, pp. 276–289, 2018.
  6. [6]H. Yuan, F. Li, Y. Wei, and J. Zhu, “Novel linearized power flow and linearized opf models for active distribution networks with application in distribution lmp,” IEEE Transactions on Smart Grid, vol. 9, no. 1, pp. 438–448, 2018.
  7. [7]S. Huang, Q. Wu, S. S. Oren, R. Li, and Z. Liu, “Distribution locational marginal pricing through quadratic programming for congestion management in distribution networks,” IEEE Transactions on Power Systems, vol. 30, no. 4, pp. 2170–2178, 2015.DOI
  8. [8]Y. Wang, Y. He, Q. Duan, H. Wang, and P. Bie, “Distribution locational marginal pricing for active network management considering high penetration of distributed energy resources,” in 2019 IEEE PES Asia-Pacific Power and Energy Internet and Energy System Integration (EI2), 2019, pp. 648–653.DOI
  9. [9]C. B. Domenech, J. Naughton, S. Riaz, and P. Mancarella, “Towards distributed energy markets: Accurate and intuitive dlmp decomposition,” IEEE Transactions on Energy Markets, Policy and Regulation, vol. 2, no. 2, pp. 240–253, 2024.
  10. [10]H. Wu, Y. Yuan, X. Zhang, J. Zhu, and X. Luo, “Distribution locational marginal pricing for energy storage through robust optimization,” in 2019 IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC), 2019, pp. 1–5.DOI
  11. [11]S. Hanif, H. B. Gooi, T. Massier, T. Hamacher, and T. Reindl, “Distributed congestion management of distribution grids under robust flexible buildings operations,” IEEE Transactions on Power Systems, vol. 32, no. 6, pp. 4600–4613, 2017.
  12. [12]P. Scott, D. Gordon, E. Franklin, L. Jones, and S. Thiébaux, “Network-aware coordination of residential distributed energy resources,” IEEE Transactions on Smart Grid, vol. 10, no. 6, pp. 6528–6537, 2019.DOI
  13. [13]L. Wang, M. Jacobs, P. F. Austnes, and M. Paolono, “Local market-aware optimal allocation of energy storage systems considering price fairness in power distribution networks,” Sustainable Energy, Grids and Networks, vol. 42, p. 101648, 2025. [Online]. Available: https://www.sciencedirect.com/science/article/pii/S235246772500030XDOI
  14. [14]S. Boyd, N. Parikh, E. Chu, B. Peleato, and J. Eckstein, Distributed Optimization and Statistical Learning via the Alternating Direction Method of Multipliers, 2011.
  15. [15]T. Erseghe, “Distributed optimal power flow using admm,” IEEE Transactions on Power Systems, vol. 29, no. 5, pp. 2370–2380, 2014.
  16. [16]R. Gupta, F. Sossan, E. Scolari, E. Namor, L. Fabietti, C. Jones, and M. Paolone, “An admm-based coordination and control strategy for pv and storage to dispatch stochastic prosumers: Theory and experimental validation,” in 2018 Power Systems Computation Conference (PSCC). IEEE, 2018, pp. 1–7.DOI
  17. [17]H. Huang and W. Zhang, “Economic evaluation of distributed resources by locational marginal price,” in 2023 IEEE Sustainable Power and Energy Conference (iSPEC), 2023, pp. 1–6.DOI
  18. [18]P. Grammatikos, A. M. Ali, and F. Sossan, “Formulation and experimental validation of price-based control of flexible prosumers in distribution grids with the alternating direction method of multipliers (unpublished),” Aug. 2025. [Online]. Available: http://dx.doi.org/10.36227/techrxiv.175615778.86522040/v1
  19. [19]D. Gebbran, S. Mhanna, Y. Ma, A. C. Chapman, and G. Verbič, “Fair coordination of distributed energy resources with volt-var control and pv curtailment,” Applied Energy, vol. 286, p. 116546, 2021. [Online]. Available: https://www.sciencedirect.com/science/article/pii/S0306261921000933
  20. [20]A. Kotsonias, L. Hadjidemetriou, M. Asprou, and C. G. Panayiotou, “Increasing the fairness of photovoltaic curtailments for voltage management in distribution grids,” in 2024 IEEE PES Innovative Smart Grid Technologies Europe (ISGT EUROPE), 2024, pp. 1–5.DOI
  21. [21]R. K. Gupta and D. K. Molzahn, “Improving fairness in photovoltaic curtailment via feedback-driven daily topology reconfiguration in power distribution networks,” Applied Energy, vol. 400, p. 126543, 2025. [Online]. Available: https://www.sciencedirect.com/science/article/pii/S0306261925012735DOI
  22. [22]A. K. Zarabie, S. Das, and M. N. Faqiry, “Fairness-regularized dlmp-based bilevel transactive energy mechanism in distribution systems,” IEEE Transactions on Smart Grid, vol. 10, no. 6, pp. 6029–6040, 2019.
  23. [23]L. Ziovani, L. Hadjidemetriou, P. Kolios, A. Astolfi, E. Kyriakides, and S. Timotheou, “Energy management and control of photovoltaic and storage systems in active distribution grids,” IEEE Transactions on Power Systems, vol. 37, no. 3, pp. 1956–1968, 2022.
  24. [24]K. Christakou, J.-Y. LeBoudec, M. Paolone, and D.-C. Tomozei, “Efficient computation of sensitivity coefficients of node voltages and line currents in unbalanced radial electrical distribution networks,” IEEE Transactions on Smart Grid, vol. 4, no. 2, pp. 741–750, 2013.DOI
  25. [25]P. Grammatikos, A. M. Ali, and F. Sossan, “Measurement-based line-impedance estimation in the absence of phasor measurement units,” in 2025 IEEE Kiel PowerTech, 2025, pp. 1–6.arxiv.org/abs/2504.21606

Paper details

vlnc:W_382fyg3f
Version
v1 · latest
Published
Fresh — added to the Hub within the last 30 days
Added
License
CC BY 4.0
Usage

views · 0

downloads · 0

A view counts once per browser per day, a download each time the PDF is requested.

  • Engineering

Not recorded for this paper

View statement
Looking for related papers…
Contents