Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

Abstract

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

**Index Terms—**Data center, generation expansion planning, transmission expansion planning, unit commitment.

Nomenclature

Sets and Indices

N\mathcal{N} — Set of buses, indexed by nn.

L\mathcal{L} — Set of transmission corridors, indexed by jj.

G\mathcal{G} — Set of existing generators, indexed by gg.

GC\mathcal{G}^{C} — Set of candidate generators, indexed by gg.

S\mathcal{S} — Set of planning scenarios, indexed by ss.

T\mathcal{T} — Set of hourly time steps {1,…,T}\{1,\ldots,T\}, indexed by tt.

IS,IW\mathcal{I}^{S},\mathcal{I}^{W} — Sets of solar / wind sites, indexed by ii.

Gn,GnC\mathcal{G}_{n},\mathcal{G}^{C}_{n} — Existing / candidate generators at bus nn.

Ln+,Ln−\mathcal{L}^{+}_{n},\mathcal{L}^{-}_{n} — Lines entering / leaving bus nn.

InS,InW\mathcal{I}^{S}_{n},\mathcal{I}^{W}_{n} — Solar / wind sites connected to bus nn.

yy — Planning stage index.

qq — Auxiliary time index used in min up/down-time constraints.

y′y' — Dummy summation variable over years within a planning stage.

kk — Candidate parallel circuit index on a corridor.

Investment Decision Variables

zj,kz_{j,k} — Binary; 1 if the kk-th candidate circuit on corridor jj is built.

xgx_g — Binary; 1 if candidate generator gg is built.

Operational Variables (per scenario ss, hour tt)

Pg,s,tP_{g,s,t} — Power output of generator gg.

ug,s,tu_{g,s,t} — Binary; commitment status of generator gg.

vg,s,tv_{g,s,t} — Binary; startup indicator of generator gg (vg,s,t=1v_{g,s,t}=1 when gg transitions from offline to online).

θn,s,t\theta_{n,s,t} — Voltage angle at bus nn.

Pj,s,tjP^{j}_{j,s,t} — Total active power flow on corridor jj.

ϕj,k,s,t\phi_{j,k,s,t} — Auxiliary angle variable for the kk-th candidate circuit on corridor jj.

Pi,s,tS,Pi,s,tWP^{S}_{i,s,t},P^{W}_{i,s,t} — Solar / wind dispatch at site ii.

Cost Variables

CinvC_{\mathrm{inv}} — Total capital investment cost ($).

CopC_{\mathrm{op}} — Net present value of total operating cost ($).

Parameters

TT — Number of hourly time steps per representative day (T=24T=24).

cjL,cgGc^{L}_{j},c^{G}_{g} — Investment cost of candidate line / candidate gen.

cgnl,cgsu,cgstc^{nl}_{g},c^{su}_{g},c^{st}_{g} — Variable, no-load, startup cost of gen. gg.

Pgmax⁡,Pgmin⁡P^{\max}_{g},P^{\min}_{g} — Max/min output of gen. gg.

Rghr,RgsrR^{hr}_{g},R^{sr}_{g} — Hourly ramp / startup and shutdown ramp rate of gen. gg.

Tgup,TgdnT^{up}_{g},T^{dn}_{g} — Min up-time / down-time of gen. gg.

xjx_j — Series reactance of corridor jj.

bj,Pˉjb_j,\bar{P}_{j} — Reciprocal of series reactance (bj=1/xjb_j=1/x_j) and thermal rating of corridor jj.

KjK_j — Maximum number of candidate parallel circuits on corridor jj.

fj,tjf_j,t_j — From-bus / to-bus index of corridor jj.

wsw_s — NPV weight of scenario ss.

rr — Annual discount rate.

ystart,yendy_{\mathrm{start}},y_{\mathrm{end}} — Start / end year of a planning stage.

DseasonD_{\mathrm{season}} — Number of days in the corresponding season.

Dn,s,tD_{n,s,t} — Conventional load at bus nn.

DnDCD^{DC}_{n} — Data center load at bus nn (constant).

Pˉi,s,tS\bar{P}^{S}_{i,s,t} — Available solar output at site ii, scenario ss, hour tt.

Pˉi,s,tW\bar{P}^{W}_{i,s,t} — Available wind output at site ii, scenario ss, hour tt.

MM — Big-M constant.

Introduction

The proliferation of cloud computing and artificial intelligence has driven rapid growth in data center electricity demand. In the United States, data center energy consumption is projected to reach 325–580 TWh by 2028, representing approximately 6.7%–12% of total national electricity demand [1]. Individual hyperscale facilities range from 100 MW to 1,000 MW in capacity [2], placing significant pressure on local transmission and generation infrastructure [3].

Grid infrastructure planning—comprising Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP)—has been extensively studied in the literature. To accommodate future load growth, TEP determines optimal network reinforcement [4], while GEP identifies the type, capacity, and location of new generation resources. Co-optimization of TEP and GEP captures the interdependency between generation siting and network capacity, yielding more cost-effective plans than sequential approaches [5]. Unit Commitment (UC) is widely embedded as the operational subproblem to ensure candidate plans satisfy generator operating constraints—including minimum up/down times, ramping limits, and startup costs—and system security requirements [6].

Recent studies have examined data center demand response [7], [8] and the potential of spatial and temporal load flexibility to reduce operating costs [9]. However, how large-scale data center interconnection influences optimal TEP and GEP decisions remains largely underexplored.

This paper addresses this gap by formulating a co-optimized Generation and Transmission Expansion Planning (GTEP) model with embedded UC to examine how large data center load sited at multiple buses affects grid expansion decisions. On the modified IEEE 24-bus Reliability Test System (RTS-24), a baseline case is compared against a scenario with 500 MW of data center load allocated across four buses, about 17.5% of the base-year peak (2,850 MW), comparable to typical hyperscale interconnection requests in the Electric Reliability Council of Texas (ERCOT) system [2], [10]. Bus allocation follows a priority-based approach using practical siting criteria [2], [11], as detailed in Section III-D. The main contributions are:

  1. A co-optimized GTEP framework with embedded UC that captures both the capital and multi-year operating costs of data center integration.

  2. Quantification of the incremental infrastructure cost of large-scale data center load, decomposed into transmission, generation, and operational components.

  3. Analysis of how data center siting alters the spatial pattern of optimal investment, revealing cases where strategically sited generation substitutes for transmission reinforcement.

Problem Formulation

The proposed GTEP model co-optimizes transmission and generation expansion over a 15-year planning horizon, with operational feasibility verified through embedded UC. The objective minimizes capital investment cost plus the net present value (NPV) of operating costs. All symbols are defined in the Nomenclature section.

Planning Horizon and Scenario Structure

The 15-year horizon is discretized into five planning stages, each spanning a 3-year block. Within each stage, four representative days capture seasonal variation (Summer, Fall, Winter, Spring), each with T=24T = 24 hourly steps, yielding ∣S∣=20|\mathcal{S}| = 20 seasonal scenarios. Each scenario is weighted by:

ws=(∑y′=ystartyend1(1+r)y′)⋅Dseason(1)w_s = \left(\sum_{y'=y_{\mathrm{start}}}^{y_{\mathrm{end}}}\frac{1}{(1+r)^{y'}}\right)\cdot D_{\mathrm{season}} \tag*{(1)}

where rr is the discount rate and DseasonD_{\mathrm{season}} is the number of days in the season (91 or 92).

Objective Function

The objective minimizes total system cost, comprising capital investment and the NPV of operating cost:

min⁡Cinv+Cop(2)\min\quad C_{\mathrm{inv}} + C_{\mathrm{op}} \tag*{(2)}

Capital investment includes all selected candidate transmission circuits and generators:

Cinv=∑j∈LCjL∑kzj,k+∑g∈GCCgGxg(3)C_{\mathrm{inv}} = \sum_{j\in\mathcal{L}} C^L_j\sum_k z_{j,k} + \sum_{g\in\mathcal{G}^C} C^G_g x_g \tag*{(3)}

Operating cost includes variable generation, no-load, and startup costs across all representative scenarios and hours:

Cop=∑s∈Sws∑t∈T∑g∈G∪GC(cgvpg,s,t+cgnlug,s,t+cgsuvg,s,t)(4)C_{\mathrm{op}} = \sum_{s\in\mathcal{S}} w_s\sum_{t\in\mathcal{T}}\sum_{g\in\mathcal{G}\cup\mathcal{G}^C}\left(c^v_g p_{g,s,t}+c^{nl}_g u_{g,s,t}+c^{su}_g v_{g,s,t}\right) \tag*{(4)}

zj,kz_{j,k} and xgx_g are time-invariant, so any asset built is in service throughout the horizon. Accordingly, CinvC_{\mathrm{inv}} is incurred at t=0t=0 and left undiscounted, whereas CopC_{\mathrm{op}} in (4) is discounted at rate rr through the scenario weights wsw_s.

Transmission Expansion Constraints

Big-M Linearization for Candidate Lines

  1. Big-M Linearization for Candidate Lines: Each corridor jj may receive up to KjK_j identical parallel circuits, indexed by k=1,…,Kjk=1,\ldots,K_j, with build decision zj,kz_{j,k}. The auxiliary variable ϕj,k,s,t\phi_{j,k,s,t} linearizes zj,k(θfj,s,t−θtj,s,t)z_{j,k}(\theta_{f_j,s,t}-\theta_{t_j,s,t}): it equals the corridor angle difference when zj,k=1z_{j,k}=1 and is zero otherwise, so each candidate circuit carries flow only when built:

ϕj,k,s,t≤(θfj,s,t−θtj,s,t)+2M(1−zj,k)(5)\phi_{j,k,s,t}\leq(\theta_{f_j,s,t}-\theta_{t_j,s,t})+2M(1-z_{j,k}) \tag*{(5)}
ϕj,k,s,t≥(θfj,s,t−θtj,s,t)−2M(1−zj,k)(6)\phi_{j,k,s,t}\geq(\theta_{f_j,s,t}-\theta_{t_j,s,t})-2M(1-z_{j,k}) \tag*{(6)}
−Mzj,k≤ϕj,k,s,t≤Mzj,k(7)-Mz_{j,k}\leq\phi_{j,k,s,t}\leq Mz_{j,k} \tag*{(7)}
zj,k≤zj,k−1,k≥2(8)z_{j,k}\leq z_{j,k-1},\qquad k\geq2 \tag*{(8)}

The ordering constraint (8) removes equivalent permutations among identical candidate circuits by requiring them to be built sequentially.

DC Power Flow and Thermal Limits

  1. DC Power Flow and Thermal Limits: The corridor flow sums the existing circuit and all built candidates, and the thermal limit scales with the circuits in service:

Pj,s,tf=bj[(θfj,s,t−θtj,s,t)+∑kϕj,k,s,t](9)P^f_{j,s,t}=b_j\left[(\theta_{f_j,s,t}-\theta_{t_j,s,t})+\sum_k\phi_{j,k,s,t}\right] \tag*{(9)}
−Pˉj(1+∑kzj,k)≤Pj,s,tf≤Pˉj(1+∑kzj,k)(10)-\bar{P}_j\left(1+\sum_k z_{j,k}\right)\leq P^f_{j,s,t}\leq\bar{P}_j\left(1+\sum_k z_{j,k}\right) \tag*{(10)}

with reference bus θ1,s,t=0\theta_{1,s,t}=0. Candidate circuits are identical to the existing line (same bjb_j, Pˉj\bar{P}_j); the case study uses Kj=1K_j=1.

Generation Expansion Constraints

Candidate generators can only be committed if built:

ug,s,t≤xg,∀g∈GC, s∈S, t∈T(11)u_{g,s,t} \le x_g,\quad\forall g \in\mathcal{G}^{C},\ s \in\mathcal{S},\ t \in\mathcal{T} \tag*{(11)}

Unit Commitment Constraints

The following constraints apply to all g∈G∪GCg \in\mathcal{G} \cup\mathcal{G}^{C}, s∈Ss \in\mathcal{S}, t∈Tt \in\mathcal{T}. Each representative day is treated as a cyclic TT-hour period with wrap-around constraints linking hour TT to hour 1.

Generation Output Limits

A committed generator operates between its minimum and maximum output limits; an offline unit produces zero power.

Pgmin⁡ug,s,t≤Pg,s,t≤Pgmax⁡ug,s,t(12)P_{g}^{\min}u_{g,s,t} \le P_{g,s,t} \le P_{g}^{\max}u_{g,s,t} \tag*{(12)}

Startup Logic

The startup variable is activated when a unit transitions from offline to online, including across the cyclic day boundary.

vg,s,t≥ug,s,t−ug,s,t−1,t≥2(13)v_{g,s,t} \ge u_{g,s,t} - u_{g,s,t-1},\quad t \ge2 \tag*{(13)}
vg,s,1≥ug,s,1−ug,s,T(14)v_{g,s,1} \ge u_{g,s,1} - u_{g,s,T} \tag*{(14)}

Ramp-Up Constraints

Output increases are limited by the normal hourly ramp rate and the startup ramp capability.

Pg,s,t−Pg,s,t−1≤Rghrug,s,t−1+Rgsrvg,s,t,t≥2(15)P_{g,s,t} - P_{g,s,t-1} \le R_{g}^{hr}u_{g,s,t-1} + R_{g}^{sr}v_{g,s,t},\quad t \ge2 \tag*{(15)}
Pg,s,1−Pg,s,T≤Rghrug,s,T+Rgsrvg,s,1(16)P_{g,s,1} - P_{g,s,T} \le R_{g}^{hr}u_{g,s,T} + R_{g}^{sr}v_{g,s,1} \tag*{(16)}

Ramp-Down Constraints

Similarly, output decreases are limited by the hourly ramp rate and shutdown ramp capability.

Pg,s,t−1−Pg,s,t≤Rghrug,s,t+Rgsr(vg,s,t−ug,s,t+ug,s,t−1),t≥2(17)\begin{aligned} P_{g,s,t-1} - P_{g,s,t} &\le R_{g}^{hr}u_{g,s,t} \\ &\quad+ R_{g}^{sr}(v_{g,s,t} - u_{g,s,t} + u_{g,s,t-1}),\quad t \ge2 \tag*{(17)} \end{aligned}
Pg,s,T−Pg,s,1≤Rghrug,s,1+Rgsr(vg,s,1−ug,s,1+ug,s,T)(18)\begin{aligned} P_{g,s,T} - P_{g,s,1} &\le R_{g}^{hr}u_{g,s,1} \\ &\quad+ R_{g}^{sr}(v_{g,s,1} - u_{g,s,1} + u_{g,s,T}) \tag*{(18)} \end{aligned}

Minimum Up/Down-Time Constraints

A generator must remain online for at least TgupT_{g}^{up} hours after startup:

∑q=t−Tgup+1tvg,s,q≤ug,s,t,t≥Tgup(19)\sum_{q=t-T_{g}^{up}+1}^{t} v_{g,s,q} \le u_{g,s,t},\quad t \ge T_{g}^{up} \tag*{(19)}
∑q=T+t−Tgup+1Tvg,s,q+∑q=1tvg,s,q≤ug,s,t,t<Tgup(20)\sum_{q=T+t-T_{g}^{up}+1}^{T} v_{g,s,q} + \sum_{q=1}^{t} v_{g,s,q} \le u_{g,s,t},\quad t < T_{g}^{up} \tag*{(20)}

Similarly, it must remain offline for at least TgdnT_{g}^{dn} hours after shutdown:

∑q=t+1t+Tgdnvg,s,q≤1−ug,s,t,t≤T−Tgdn(21)\sum_{q=t+1}^{t+T_{g}^{dn}} v_{g,s,q} \le1-u_{g,s,t},\quad t \le T-T_{g}^{dn} \tag*{(21)}
∑q=t+1Tvg,s,q+∑q=1Tgdn−(T−t)vg,s,q≤1−ug,s,t,t>T−Tgdn(22)\sum_{q=t+1}^{T} v_{g,s,q} + \sum_{q=1}^{T_{g}^{dn}-(T-t)} v_{g,s,q} \le1-u_{g,s,t},\quad t > T-T_{g}^{dn} \tag*{(22)}

Renewable Energy Constraints

Solar and wind output is bounded by available resource; curtailment is permitted:

0≤Pi,s,tS≤P‾i,s,tS,∀i∈IS(23)0 \le P_{i,s,t}^{S} \le\overline{P}_{i,s,t}^{S},\quad\forall i \in\mathcal{I}^{S} \tag*{(23)}
0≤Pi,s,tW≤P‾i,s,tW,∀i∈IW(24)0 \le P_{i,s,t}^{W} \le\overline{P}_{i,s,t}^{W},\quad\forall i \in\mathcal{I}^{W} \tag*{(24)}

Nodal Power Balance with Data Center Load

Power balance at each bus nn, scenario ss, and hour tt:

∑g∈Gn∪GnCPg,s,t+∑i∈InSPi,s,tS+∑i∈InWPi,s,tW+∑j∈Ln+Pj,s,tf−∑j∈Ln−Pj,s,tf=Dn,s,t+DnDC(25)\sum_{g \in\mathcal{G}_{n}\cup\mathcal{G}_{n}^{C}} P_{g,s,t} +\sum_{i \in\mathcal{I}_{n}^{S}} P_{i,s,t}^{S} +\sum_{i \in\mathcal{I}_{n}^{W}} P_{i,s,t}^{W} +\sum_{j \in\mathcal{L}_{n}^{+}} P_{j,s,t}^{f} -\sum_{j \in\mathcal{L}_{n}^{-}} P_{j,s,t}^{f} = D_{n,s,t}+D_{n}^{DC} \tag*{(25)}

Conventional load Dn,s,tD_{n,s,t} scales with a compound annual growth rate and varies by season and hour. Data center load is constant across all hours and scenarios, reflecting fixed-capacity interconnection agreements (DnDC=0D_{n}^{DC}=0 at buses without a data center).

For the locational marginal price (LMP) analysis in Section IV-C, all binary investment and unit-commitment decisions are fixed at their mixed-integer solution values, and the resulting linear program (LP) is re-solved. The LMP at bus nn, scenario ss, and hour tt is obtained from the dual multiplier of (25), divided by ωs\omega_{s} to recover the marginal energy price in $/MWh from the scenario-weighted dual.

Test System and Case Setup

IEEE RTS 24-Bus System

The test system is the modified IEEE RTS-24 bus system, comprising 24 buses, 34 transmission corridors, and 32 existing generating units with a total capacity of 3,405 MW. The system spans two voltage levels: 138 kV (Buses 1–10) and 230 kV (Buses 11–24), interconnected by transformers. Peak conventional load is 2,850 MW, yielding a base-case reserve margin of 19.5%. Load at each bus scales with a compound annual growth rate of 1.5%/year, and a discount rate of 5% (the rate rr in (1) is applied across the 15-year planning horizon, which comprises five planning stages and four representative days (Summer, Fall, Winter, Spring) to capture seasonal load and renewable variability, yielding 20 seasonal scenarios. Data center loads are assumed fully commissioned prior to the first planning milestone and remain at 500 MW across all five stages. All mixed-integer programs are solved with Gurobi 11.0 using a 1% optimality gap.

Renewable Energy Resources

Five renewable energy sites are added to the system, with hourly output profiles derived from ERCOT historical capacity factor data [12, 13], as summarized in Table I.

SiteBusCapacity (MW)TypeAnnual Capacity Factor (%)
Solar-11200Solar26
Solar-218200Solar26
Solar-322200Solar26
Wind-13200Wind38
Wind-217200Wind38
Total1,000

Table I. Renewable Energy Sites

Solar generation follows a diurnal bell-curve pattern with midday peaks and pronounced seasonal variation, exhibiting higher seasonal-average capacity factors in summer than in winter [13]. Wind generation exhibits an anti-correlated temporal profile relative to solar, characterized by elevated output during nighttime hours and transitional seasons (spring and fall), reflecting the complementary nature of co-located wind and solar resources in the ERCOT region [13].

Candidate Expansion Assets

Transmission candidates comprise one additional parallel circuit on each of the 34 existing corridors (Kj=1K_j = 1), identical to the in-service circuit in both susceptance and thermal rating. Investment costs are derived from industry exploratory benchmarks [14]: $2.3 M/mile for 138 kV lines and $2.5 M/mile for 230 kV lines, scaled by corridor length, while corridors interconnecting the two voltage levels are modeled as transformers with a flat cost of $25 M per unit. Restricting each corridor to a single reinforcement keeps the candidate set tractable while still allowing the optimizer to relieve an individual corridor bottleneck.

Generation candidates comprise 18 combined-cycle gas turbine (CCGT) units, modeled as two identical units at each of nine selected buses. Each unit is rated at 400 MW with a 100 MW minimum stable output, an assumed overnight capital cost of $368 M, a marginal operating cost of $40/MWh (inclusive of fuel and variable operations and maintenance (O&M) costs), and minimum up/down times of 4 hours. This operating range allows a committed unit to supply its co-located load and, when economical, export surplus power to neighboring buses—a feature that becomes important in the transmission–generation substitution discussed in Section IV-B. The candidate buses span both voltage levels (Buses 1, 2, and 7 at 138 kV; Buses 13, 15, 18, 21, 22, and 23 at 230 kV) and cover major existing generation centers, allowing the optimizer to compare local generation additions with network reinforcement across the system. Generation cost parameters are treated as fixed modeling assumptions of the same order of magnitude as reported industry benchmarks [15]; therefore, the qualitative results depend primarily on their relative rather than exact absolute magnitudes.

Data Center Load Allocation

Because hyperscale data centers operate as constant, around-the-clock loads, bus selection prioritizes the ability to serve continuous, non-deferrable demand rather than to absorb intermittent renewable output. Candidate buses are ranked by two primary criteria—voltage level, favoring 230 kV buses over the thermally limited 138 kV sub-network, and dispatchable capacity headroom, which supports local supply of the constant load and can reduce new-infrastructure needs—and two secondary criteria, renewable co-location, which can reduce local curtailment, and network connectivity, which distributes power flows across multiple corridors.

Applying these criteria, 500 MW (≈17.5%\approx17.5\% of base-year peak) is distributed across four buses, as summarized in Table II. Bus 18 receives the largest share (200 MW) as the only selected 230 kV bus combining 400 MW of dispatchable generation with 200 MW of co-located solar. Bus 13 receives 150 MW, supported by the system’s largest dispatchable generation cluster (3×1973 \times197 MW). Bus 15 receives 100 MW and uses its connections to Buses 16, 21, and 24 to redistribute power flows. Bus 1 receives the smallest share (50 MW); despite co-located solar, its location in the 138 kV sub-network makes it less suitable for a large continuous interconnection. Overall, the 230 kV sub-network hosts 90% of the data center load. Data center loads are modeled as constant-power withdrawals invariant across time and planning years, reflecting fully firm interconnection service.

BuskVConv. GeneratorsTotal (MW)RE Co-loc.Conn. LinesData Center (MW)
182301 × 400400Solar 2002200
132303 × 197591—3150
152305 × 32, 1 × 155215—3100
11382 × 20, 2 × 76192Solar 200350
Total500

Table 2. Data Center Load Allocation Across Candidate Buses.

Results and Discussion

Expansion Decisions

Table III summarizes the physical expansion decisions, cost components, and renewable curtailment for the base and data center cases, while Figure 1 visualizes the corresponding cost comparison. The two cases differ in both the type of asset selected and the composition of total system cost.

Cost comparison of expansion planning results between the base case and the data center case

Figure 1. Cost comparison of expansion planning results between the base case and the data center case.

MetricBase CaseData Center CaseDiff.
New transmission lines10−1
New generators01+1
Line investment ($M) | 85.0 | 0 | −85.0
Gen. investment ($M) | 0 | 368.0 | +368.0
Total investment ($M) | 85.0 | 368.0 | +283.0
NPV operating cost ($M) | 2,826.5 | 4,337.1 | +1,510.6
Total NPV cost ($M) | 2,911.5 | 4,705.1 | +1,793.6
Solar curtailment (%)000
Wind curtailment (%)00.1+0.1

Table 3. Expansion Planning Results: Base Case vs. Data Center Case.

In the base case, the optimal plan builds one 230 kV230\ \mathrm{kV} circuit on corridor Bus 15→\toBus 21 at a cost of $85M and requires no new generation. The existing 3,405 MW conventional fleet, together with 1,000 MW of renewable capacity, provides sufficient headroom to serve conventional load as its peak reaches 3,511 MW in the final year. Solar and wind curtailment are both zero.

The data center case yields a fundamentally different plan: no new transmission is built, and one 400 MW CCGT is installed at Bus 15 for $368M. The 500 MW constant load raises total investment by $283.0M and the NPV operating cost by $1,510.6M, producing a total NPV cost increase of $1,793.6M (+61.6%). Operating cost accounts for 84.2% of this increment, reflecting continuous fuel consumption across hours, seasons, and planning stages. Renewable curtailment remains negligible: solar curtailment stays at zero, and wind curtailment rises to only 0.1%.

Transmission–Generation Substitution

A notable finding is that data center integration eliminates the need for transmission reinforcement entirely: the base case reinforces the 230 kV230\ \mathrm{kV} network (Bus 15→\to21, $85M) to relieve load-growth congestion, whereas the data center case builds no new transmission and instead invests $368M in a 400 MW CCGT at Bus 15. With 100 MW of local data center load and connections to three neighboring buses (16, 21, and 24), the CCGT simultaneously serves local demand, exports surplus power, and relieves the corridor that drove the base-case reinforcement—its 400 MW capacity, four times the local load, confirms a system-wide role. Strategically sited generation can thus substitute for transmission investment when data center load reshapes the supply–demand balance.

LMP Impact Analysis

Figure 2 presents the nodal LMP comparison across all 24 buses between the base case and the data center case.

Comparison of nodal LMPs between the base case and the data center case

Figure 2. Comparison of nodal LMPs between the base case and the data center case. Dark red bars indicate data center-hosting buses with their allocated load.

Data center integration raises the system-average LMP from $29.76/MWh to $43.20/MWh (+45.2%), reflecting two compounding effects: the additional 500 MW of constant load requires higher-cost dispatch in every hour, and the two cases differ in network topology—the base-case plan reinforces the 230 kV230\ \mathrm{kV} Bus 15–21 corridor and yields more uniform LMPs, whereas the data center case serves the load with a new CCGT at Bus 15 and builds no transmission.

The increase is spatially non-uniform. Buses near the new CCGT record the lowest LMPs—Bus 21 ($36.95), Bus 24 ($37.24), Bus 18 ($37.68), Bus 15 ($39.81)—while electrically remote 138 kV buses record the highest: Bus 9 ($46.67), Buses 7 and 8 ($46.40), Bus 4 ($46.05). Buses 4, 8, and 9 host no candidate generation and can be relieved only through transmission, which the optimal plan does not reinforce; their elevated prices reflect congestion from constrained corridors. Absolute LMP levels are conditional on the candidate investment set ($40/MWh CCGTs and single parallel circuits per corridor). Overall, co-optimized siting suppresses prices locally around the new unit while amplifying network-wide differentials.

Renewable Energy Impact

Solar curtailment remains zero in both cases; wind curtailment rises marginally to 0.1% under data center integration, totaling only 67 MWh in two evening hours of a single spring scenario. It originates from localized congestion at Bus 3 (Wind-1 site), where corridor Bus 3→\toBus 9 reaches its 175 MW thermal limit and Bus 3→\toBus 24 operates at 99.1% of its 400 MW rating. With ∼1,938\sim1{,}938 MW of conventional headroom available, the curtailment reflects local bottlenecks rather than oversupply; the optimizer does not reinforce these corridors as the investment cost exceeds the recovered wind energy value.

Data center load thus acts as a net demand increase rather than a source of conflict with renewable integration, though whether this holds at higher renewable penetrations (above the current 1,000 MW, ∼35%\sim35\% of base-year peak) warrants further investigation.

Conclusion

This paper presented a UC-embedded GTEP co-optimization framework to quantify the grid expansion cost of large-scale data center load. On the modified IEEE RTS-24 system, integrating 500 MW of data center load increases the 15-year NPV total system cost by $1,794M (+61.6%), with operating costs dominating (84.2%) over capital investment (15.8%). The data center eliminates base-case transmission reinforcement and instead triggers a 400 MW CCGT at a well-connected bus, demonstrating that strategically sited generation can substitute for transmission investment. Renewable curtailment remains negligible (0.1%), attributable to localized congestion rather than system-wide oversupply. Future work will incorporate N−1N-1 contingency constraints and data center load flexibility as planning decision variables.

Acknowledgment

This research was supported in part by the University of Houston Energy Transition Institute Seed Grant Program.

References

References

  1. [1]A. Shehabi, S. J. Smith, A. Hubbard, A. Newkirk, N. Lei, M. A. Siddik, B. Holecek, J. G. Koomey, E. R. Masanet, and D. A. Sartor, “2024 United States Data Center Energy Usage Report,” Lawrence Berkeley National Laboratory, Berkeley, CA, USA, Tech. Rep. LBNL-2001637, Dec. 2024.
  2. [2]Electric Power Research Institute (EPRI), “Powering intelligence: Analyzing artificial intelligence and data center energy consumption,” Electric Power Research Institute (EPRI), Tech. Rep. 3002028905, May 2024.
  3. [3]S. Bessaparais, S. Ramirez, E. Zhao, Y. Zheng, K. Patel, and I. Riu, “Forecasting large loads in the age of AI and data centers,” Energy and Environmental Economics, Inc. (E3), White Paper, Dec. 2025.
  4. [4]X. Li and Q. Xia, “Transmission expansion planning with seasonal network optimization,” in 2020 IEEE Power & Energy Society Innovative Smart Grid Technologies Conference (ISGT), 2020, pp. 1–5.arxiv.org/abs/1911.12962
  5. [5]S. You, S. W. Hadley, M. Shankar, and Y. Liu, “Co-optimizing generation and transmission expansion with wind power in large-scale power grids—implementation in the US eastern interconnection,” Electric Power Systems Research, vol. 133, pp. 209–218, 2016.DOI
  6. [6]A. V. Ramesh and X. Li, “Spatio-temporal deep learning-assisted reduced security-constrained unit commitment,” IEEE Transactions on Power Systems, vol. 39, no. 2, pp. 4735–4746, 2024.
  7. [7]Z. Liu, A. Wierman, Y. Chen, B. Razon, and N. Chen, “Data center demand response: Avoiding the coincident peak via workload shifting and local generation,” Performance Evaluation, vol. 70, no. 10, pp. 770–791, 2013, proceedings of IFIP Performance 2013 Conference.
  8. [8]H. Wang, J. Huang, X. Lin, and H. Mohsenian-Rad, “Proactive demand response for data centers: A win-win solution,” IEEE Transactions on Smart Grid, vol. 7, no. 3, pp. 1584–1596, 2016.DOI
  9. [9]H. Wan, L. Fang, and X. Li, “Grid operational benefit analysis of data center spatial flexibility: Congestion relief, renewable energy curtailment reduction, and cost saving,” in 2026 IEEE Power & Energy Society General Meeting (PESGM), Montreal, QC, Canada, Jul. 2026.arxiv.org/abs/2511.08759
  10. [10]P. Vegas, “ERCOT update: House committee on state affairs,” Presentation, Electric Reliability Council of Texas (ERCOT), Apr. 2026, Texas House Committee on State Affairs Hearing, April 9, 2026.
  11. [11]A. Hajihasani and M. Modaresi, “Optimal placement of data centers to support power distribution networks using intelligent algorithms with economic indicators,” arXiv preprint arXiv:2512.21987, 2025. [Online]. Available: https://arxiv.org/abs/2512.21987
  12. [12]K. Carden, A. Dumbrowsky, and A. Nathan, “Effective Load Carrying Capability Study: Final Report,” Astrape Consulting, prepared for Electric Reliability Council of Texas (ERCOT), Tech. Rep., Feb. 2025. [Online]. Available: https://www.ercot.com/files/docs/2025/02/12/2024ERCOT_ELCC_Study_Final_Report02112025.pdf
  13. [13]J. H. Slusarewicz and D. S. Cohan, “Assessing solar and wind complementarity in Texas,” Renewables: Wind, Water, and Solar, vol. 5, no. 1, p. 7, 2018.DOI
  14. [14]Midcontinent Independent System Operator, “Transmission cost estimation guide for MTEP24,” Midcontinent Independent System Operator (MISO), Tech. Rep., Jan. 2024. [Online]. Available: https://cdn.misoenergy.org/20240131%20PSC%20Item%20005%20Transmission%20Cost%20Estimation%20Guide%20for%20MTEP24%20-%20Redline631529.pdf
  15. [15]U.S. Energy Information Administration, “Capital cost and performance characteristics for utility-scale electric power generating technologies,” U.S. Energy Information Administration, Tech. Rep., Jan. 2024. [Online]. Available: https://www.eia.gov/analysis/studies/powerplants/capitalcost/pdf/capital_cost_AEO2025.pdf

Paper details

vlnc:W_ept49p5a
Version
v1 · latest
Published
Fresh — added to the Hub within the last 30 days
Added
License
CC BY 4.0
Usage

views · 7

downloads · 0

A view counts once per browser per day, a download each time the PDF is requested.

  • Engineering

Not recorded for this paper

View statement